Habersham outlines next steps for $52M jail project

Construction manager search could begin early next year; county also weighs temporary offices for Sheriff's Office divisions

Habersham County Manager Tim Sims presents the next steps for the proposed detention center project during the Nov. 16 commission work session. His presentation outlined the project timeline, the construction manager-at-risk selection process and options for temporarily relocating Sheriff's Office personnel. (Patrick Fargason/NowGeorgia.com)

CLARKESVILLE, Ga. — Habersham County officials are targeting early 2027 to begin the search for a construction manager for the county’s planned $52 million jail and Sheriff’s Office project, while also weighing where several Sheriff’s Office divisions will operate during construction.

County Manager Tim Sims outlined the anticipated design and procurement schedule during a Board of Commissioners work session Monday. He also discussed possible relocation options for three aging portable office trailers currently occupying the site where the new jail will be built.

The county is continuing design work with Precision Planning Inc., which commissioners selected in October for architectural and construction-phase services. Sims said the county hopes to have a final schematic design by February 2027 and issue a request for proposals for a construction manager at risk around February or March.

All dates are estimates and could change, he cautioned.

Construction manager search planned for early 2027

Under the anticipated schedule, Precision Planning will continue developing the schematic design before helping the county prepare the construction manager request for proposals. Final construction documents are expected in fall 2027.

Once selected, the construction manager will work with the architect to review the plans and identify potential cost savings through value engineering. Precision Planning will also provide construction administration throughout the project to monitor compliance with plans, specifications and applicable codes.

Sims said the county expects to advertise the RFP for at least 30 days, as required by state law and purchasing requirements. The opportunity will be advertised in the Northeast Georgian and posted on the Georgia Procurement Registry, which distributes bid notices to vendors registered for relevant work.

The county will use a three-step evaluation process. First, a review committee will score proposals based on firms’ qualifications and experience. The committee will then narrow the field to approximately three or four finalists.

If needed, finalists will be invited for interviews before the committee opens their fee proposals. Those scores will be combined with the qualifications and experience scores before the committee ranks the firms and makes a recommendation to commissioners.

Sims said the county wants a construction manager with experience building jails.

“We don’t want to hire somebody that’s never built a jail before, because from what I’ve been told, that’s kind of how we got to where we are now,” he said.

The review committee is expected to include Sheriff’s Office representatives, county purchasing staff, the county manager, the county’s capital project manager and the architect. Chairman Bruce Harkness asked Sims to include two commissioners on the panel, a request Sims accepted.

Habersham County commissioners meet Nov. 16 as a presentation on the next steps for the proposed detention center project appears on the screen. Commissioners discussed the project timeline, construction manager-at-risk selection process and temporary office space for the Sheriff’s Office. (Patrick Fargason/NowGeorgia.com)

Commissioners raise local contractor participation

Commissioner Kelly Woodall said she wants the county to make every effort to give local contractors and vendors an opportunity to compete for work on the project.

Woodall acknowledged that legal requirements may limit the county’s ability to give local businesses preferential treatment based on location, but said local participation remains important.

“It’s important to our community that people who live and work here have an opportunity to do these projects too,” she said.

Sims said the county included language in its previous RFPs for the animal control and fire/911 buildings requiring contractors to advertise and encourage local vendor participation.

He said several local businesses submitted bids on those projects. However, in some cases, including HVAC and possibly plumbing, local bids were significantly higher than competing proposals from outside the area.

The county ultimately selected the lower-cost vendors, Sims said.

Sheriff’s Office trailers must be relocated

Three portable office trailers currently house several Sheriff’s Office divisions on the property designated for the new jail. Sims said the trailers were purchased used and are now more than 30 years old.

The county has not determined whether they can be moved to another location. Sims said he recently contacted Sheriff Robin Krockum about the possibility, but their age and condition could make relocation difficult.

The offices serve patrol, investigations, the Drug Task Force and training operations. The Sheriff’s Office needs space for several employees, including six investigation offices, two Drug Task Force offices and a training area that can accommodate up to 30 people.

Harkness asked the county to have the trailers inspected soon to determine whether they are structurally sound enough to move.

“I think we’re a few months out from having to move them right now, but we will definitely get someone out there to do that,” Sims said.

One possibility is to construct a metal building on county-owned property along Harvey Adams Road, originally acquired for parks expansion. Sims said a rear entrance from the Aquatic Center parking lot could help reduce grading costs.

He said comparable 60-by-60-foot airport hangars cost an estimated $250,000 to $275,000, although a simpler building without specialized hangar doors could cost less.

Other possibilities include leasing commercial space or relocating the existing trailers if they can be moved safely.

Habersham County Commission Chairman Bruce Harkness listens during the Nov. 16 work session. Harkness asked that two commissioners serve on the selection committee for the county’s planned detention center project. (Patrick Fargason/NowGeorgia.com)

New building could eventually house Extension Services

The discussion also raised the possibility that a new building could serve a longer-term purpose after construction of the jail is complete.

Commissioner Ty Akins asked whether Extension Services and USDA offices could move into the proposed building once Sheriff’s Office personnel no longer need the temporary space.

Sims said Clarkesville remains interested in purchasing the property where those offices are currently located. He said he spoke with the city’s manager in recent days and confirmed the city is still interested if the county decides to sell or relocate the offices.

The Extension Services property is near the former courthouse site, which Clarkesville has been exploring for potential redevelopment. Sims said the city has a first right of refusal on the property under the county’s previous arrangement involving the courthouse property.

Commissioner Kelly Woodall questioned whether moving Extension Services, including its 4-H programs, to a rural setting could improve the services it offers.

Sims said the county-owned Harvey Adams Road property includes a pond and trees that could support educational activities. He also pointed to opportunities for archery and BB-gun programs.

Currently, those shooting activities take place at the fairgrounds pavilion. Sims said participants sometimes miss the wooden backstops, sending projectiles through the building and requiring repairs.

“I feel like it would because that’s an old farm over there, and there’s a pond that they could do different things,” Sims said.

He said the county would want any relocation to enhance Extension Services programming rather than disrupt it.

Sims said the county is still evaluating the options and will bring commissioners more detailed plans and cost estimates before making a decision.

Design contract already approved

The work session follows the Board’s Oct. 19 approval of a contract with Precision Planning worth up to $2,320,400 for design and construction-phase services.

Commissioners approved the agreement 3-1, with Danny McClellon opposing it after questioning the cost and whether the county should seek additional bids for the architectural work. Dustin Mealor was absent.

Sims said the contract is included in the previously approved $52 million project budget, not an additional expense. The agreement covers continued design work, preparation of construction documents and construction administration.

The county plans to build on conceptual floor plans and elevations Precision Planning developed in 2018-19 rather than begin the design process from scratch.

Don’t miss what everyone in town is talking about.

Join 4,000+ locals and choose our free newsletter covering news, events and the stories shaping our region.

This field is for validation purposes and should be left unchanged.